2025 Geothermal Drilling Cost Curves Update (NREL / Stanford Geothermal Workshop 2025)

Source: https://docs.nrel.gov/docs/fy25osti/92793.pdf

Provenance: NREL conference preprint (Stanford GW 2025), DOE-GTO funded, using Fervo-supplied well data plus Utah FORGE. Independent government-lab quantification of the EGS drilling learning curve that feeds the GETEM / SAM / ATB cost models. Retrieved via research agent; full text extracted with pdftotext.

Why drilling matters

“Drilling activities account for 30% to 57% of the cost to develop and install a geothermal plant.” The share is higher for next-generation / EGS projects.

Per-well record (El-Sadi et al. 2024 data)

WellDaysTD (ft)$/ftNote
Project Red well 17111,220994.62158 ft/day
Project Red well 25811,2111,106.74
Cape well 333.75~13,300–13,950633
Cape well 425.91472
Cape well 524.26396
Cape well 620.1346
Cape well 723.71394
Cape well 822.27357

“the Project Red well costs were close to three times the average cost of the Cape Station wells.” Inter-project learning rate ~35%.

Cape Station drilling facts

  • 1 vertical + 14 horizontals from just two pads (Frisco, Bearskin), Jun 2023–Sep 2024; TD 13,272–15,347 ft (4,045–4,678 m); laterals ~4,700 ft; max temperature 444 °F.
  • Triplet test: producing 382.9 °F (195 °C), peak >12 MWe, sustained 8–10 MWe.
  • Average ROP 70 ft/hr with 34 hr average bit life (PDC bits). Compare Utah FORGE 16B(78)-32: 102 ft/hr but 6.5 hr bit life (16 PDC bits, 10,947 ft, 75 days); Geysers GDC-36 65 ft/hr. Single-run hard-rock ROP up to 173 ft/hr at FORGE.

Model assumption changes vs GeoVision (2017)

  • ROP 25 → 75 ft/hr; casing-running speed 300 → 800 ft/hr (casing running tools); contingency 15% → 10% (Cape cumulative cost was 84% of AFE); PDC bit cost multiplier 2×.
  • Result: drilling costs 12–24% below the GeoVision baseline for vertical wells, 18–26% for horizontal wells; curves now sit between GeoVision “Baseline” and “Intermediate 1.”
  • Drivers: PDC bits, physics-based limiter redesign (mechanical specific energy), multiwell pad drilling, oil-and-gas technology transfer.
  • Caution: a 2022 attempt to lower the curves failed because Utah FORGE costs did not match its ROP gains — speed ≠ cost.

Key quotes

  • “For vertical wells, the magnitude of cost reduction ranges from 12% to 24%, while for horizontal wells, the estimated cost reduction is between 18% and 26%.”

Companion: Fervo drilling blog (12 Feb 2024)

https://fervoenergy.com/fervo-energy-drilling-results-show-rapid-advancement-of-geothermal-performance/ — fastest Cape well 21 days (70% faster than the first Red well); cost per well $9.4M → $4.8M across the first four Cape horizontals; Cape wells 2,100+ ft deeper than Red; ~70 ft/hr ROP; planned 18% learning curve, achieved ~35%.

Relevance to the cooling wiki

Fixes the cost side of “geothermal as drive heat”: the well is the dominant cost, and the well cost is now a moving target ($9.4M → $4.8M in six months at one site). Any levelized cost of geothermal cold inherits this curve.